Commercial energy storage procurement checklist for EPCs and distributors
Turn a project brief into a reviewable scope covering load data, kW and kWh, integration responsibilities, local approvals, acceptance and shipping documentation.
Reviewed 2026-11-12 · EITAI product and project records
Define the operating problem before requesting capacity
A commercial storage request should start with the site's operating objective: outage support, solar self-consumption, demand management or another defined duty. Provide interval load data where available, essential-load priorities, motor starting requirements, operating hours and expected outage patterns. Record grid voltage, phase arrangement, frequency, transformer capacity, existing PV and generator interfaces. These inputs let an EPC compare proposals on the same basis.
Specify required continuous and peak power in kW separately from stored and usable energy in kWh. For a hypothetical 30 kW load over two hours, load energy alone is 60 kWh before losses, reserve and other design allowances. This is a planning illustration, not an EITAI system recommendation. Check the recharge window and available charging power as well as discharge demand.
Agree the equipment and responsibility boundaries
Ask for a model-specific bill of materials and single-line diagram. Identify who supplies and integrates batteries, PCS or hybrid inverters, BMS, EMS, metering, switchgear, protection, cables, racks, cooling and any required fire-safety equipment. EITAI manufactures batteries; separately sourced inverters must retain their manufacturer identification. Assign ownership for design, installation, grid interface, commissioning and after-sales escalation in the project scope.
| Procurement item | Requested evidence |
|---|---|
| System scope | Exact models, quantities, ratings and exclusions |
| Site integration | Drawings, interfaces, environmental limits and responsibilities |
| Acceptance | Agreed tests, conditions, measurements and sign-off |
| Delivery | Packing list, transport requirements and destination documents |
Verify local requirements and acceptance conditions
Have the local EPC and relevant authorities identify applicable electrical, grid-connection, building and fire requirements. Requirements differ by destination and project; a certificate title on a product page is not evidence that the assembled system has local approval. Request the applicable model-specific reports and documents from the team, and have the responsible local party assess their relevance.
Define factory and site acceptance criteria before purchase. Agree measured usable energy conditions, permitted power, BMS/EMS data visibility, protection functions, alarm handling and operating modes. State test temperature, starting state of charge, measurement boundary and pass criteria. Record firmware versions, settings, serial numbers, training, manuals and handover responsibilities. A project photograph cannot replace these acceptance records.
Close the logistics and commercial document gaps
Give the team the delivery destination, access restrictions and unloading plan. Ask which transport documents, battery test summaries, safety data, packaging information and import documents are available and required for the selected shipment. Confirm responsibilities with the freight forwarder and importer. Request current project-specific quotation terms, delivery arrangements, service scope and warranty wording in writing. Use the Nigeria and Guangzhou records as references for discussing system scale, without treating their archived ratings as a design template.
FAQ
What is the minimum useful EPC enquiry package?
Provide the destination, operating objective, load data, required kW and usable kWh, grid information, existing equipment, site conditions and proposed responsibility split.
Can an existing project establish local compliance for my site?
No. Each configuration and destination needs its own assessment. Request applicable documents and have the responsible local EPC or authority evaluate them.
Which shipping documents will be supplied?
Ask the team to confirm the exact document package for the model, shipment method and destination. The freight forwarder and importer should verify the required documents before dispatch.